Vodafone

This project consisted of the fit out of the full building whilst fully occupied by the end users staff. Programming and phased handovers played a big part in the delivering of this project, as installing new plant in occupied areas had to be avoided.

What we did:

Project Name – Wythenshawe Telecoms
Contract Period - 16 weeks
Contract – Design and Build
M&E Checking Consultant - AECOM

The works that Seba-Uk Ltd completed include:

  • Comms room gas extract system and controls
  • BMS controls extensions works
  • New AHU’s
  • New AC plant
  • New tea point and toilet services
  • Modifications to local extract systems
  • Modifications to existing chilled water only FCUs
  • Modifications throughout the building to supply and extract systems
  • Full new catering plant 

Key project features:

  • Fast track fit out
  • Live environment
  • Early handover of a comms room
  • Phased handover
  • Coordination with landlords fit out contractor who was replacing main plant
  • Complex commissioning phase

When you work with us, you can expect close attention from our experienced project managers and site managers and make the most of the expertise and advice we can provide. No matter how big or small the project, we do whatever it takes to understand exactly what you need and deliver it, on time, on budget and to extremely high standard.

Contact us today to discuss your project